LONG-TERM GROUNDWATER MONITORING PLAN
BENNETT'S DUMP
BLOOMINGTON PROJECT
Monroe County, Indiana
March 2002
Viacom Inc.
Bloomington Project
[Note-To see the all tables and figures, visit the PCB Repository at the MCPL.]
1.0 Introduction
The Statement of Work (SOW) for the remedial action at Bennett's Dump was agreed to on
August 26, 1999. The SOW and the amended Record of Decision (ROD) require Viacom to
submit a Long-term Groundwater Monitoring Plan for IDEMand USEPA approval. Monroe
County is also to review and comment on this plan.
The purpose of the Long-term Groundwater Monitoring Plan is to monitor for the presence of
PCBs in the Groundwater related to the site. Per the SOW, Groundwater monitoring is to occur
quarterly until completion of a five-year review to be done under CERCLA Section 121(c) and
Section 300.430(fl(4)(ii) of the National Contingency Plan.
The SOW specifies that ~ review will occur five years after construction began at Bennett's
Dump. The remedial action at Bennett's Dump began in August 1999. Interim Groundwater
monitoring which was initiated before the remedial action has continued to the present. The
interim monitoring will continue until the Long-term Groundwater Monitoring Plan is
implemented. This plan will be reviewed in August 2004. At that time, the Consent Decree
(CD) parties will review the monitoring data and decide to maintain, reduce or eliminate the
Groundwater monitoring. Also, during the base monitoring period, changes to the plan may be
proposed and the plan changed with the consent of all the parties.
1.1 Site Location
Bennett's Dump is located in a rural setting in the central portion of Monroe County, Indiana. It is
approximately 2.5 miles northwest of the City of Bloomington, as shown in Figure 1. The site
consists of two areas. The main area is 3.5 acres in size and is located adjacent to Stout's Creek.
The adjacent land to the west of the site, across from Stout's Creek, is agricultural.
Another area, referred to as the satellite area, is located approximately one hundred feet to the
east of the main area. The satellite area is approximately one half-acre in size. The main area is
bounded by Stout's Creek to the west and quarry access roads to the south and east. Figure 2
shows a plan view of Bennett's Dump.
A third small area (approximately 30 by 60 feet), 750 feet north of the main area was to be
remediated under the original CD. A 1992 EPA sampling effort of this area showed no presence of
PCBs. Based on these results, the CD parties agreed that no further action was necessary at this
location.
1.2 Site History
Historically, land in the vicinity of Bennett's Dump was used for quarrying operations. The site is
located within a former limestone quarrying area previously known as Bennetts Quarry. Bennett's
Quarry was privately owned and operated by Mr. Edward Bennett until it was sold to the Star Stone
Company in 1987.
The quarry produced a finished building stone whose source was the Salem Limestone. Quarries
in this area also produced crushed stone for road construction, low-magnesium limestone for
cement, and high magnesium limestone for steel production and agricultural application. There is
an inactive stone mill within 50 feet of the southwest comer of the main site. The site contains
large surface and subsurface limestone quarry blocks and stone rubble, which were abandoned
during quarry operations.
In the 1960s (exact dates unknown), a portion of the quarry was used as a landfill for industrial
wastes. These wastes included Westinghouse electrical capacitors, which contained PCBs.
1.2.1 ~ On-scene Coordinator's Report
On May 12, 1983, Ron Lillich, the USEPA on-scene coordinator, conducted the initial site
assessment of Bennett's Dump at the request of the Monroe County Health Department. The
report of this site assessment is contained in the "On-scene Coordinator's Report", USEPA,
June 1983, (Reference 1).
The initial condition of this site indicated that it was an uncontrolled dumping and salvaging ground
for electrical parts. Most of the electrical parts visible at the site had been crushed, burned or
otherwise tom open, with insulator wrapping paper, ceramic bushings, and other electrical parts
scattered about the surface. The existence of stained soil was also evident on the landfill surface.
The on-scene coordinator's report also describes: 1) a small pond, possibly a spring, on the
eastside of the fill, 2) an adjoining pond draining west toward Stout's Creek, and 3) a small pond
along the west border of the site, situated between the fill and the railroad tracks. This small
pond flowed via two routes directly into Stout's Creek. The EPA sampled the water from the
pond at the time of the inspection in 1983. The 1983 sample was analyzed at 7 ppb PCB
Aroclor 1242.
1.2.2 Consent Decree
In 1985, a Consent Decree (Reference 23 was agreed to by Viacom Inc. (formerly CBS
Corporation and Westinghouse Electric Corporation), the City, State, Monroe County and EPA
(collectively known as the Consent Decree (CD) parties) that addressed the remediation of
various sites, including the Bennett's Dump site. The remedy called for closure and removal of
PCB contaminated materials within the metes and bounds of the site. Along with the removal
activities, the CD also required long-term Groundwater monitoring, sediment removal and
additional sediment monitoring in Stout's Creek.
The removal actions are summarized in the following sections.
1.2.3 Interim Remedial Measures (IRMs)
Interim remedial measures (IRMs) were completed at Bennetts Dump in two phases. The first
phase was completed by the USEPA in June 1983 as a result of the initial site assessment by the
on-scene coordinator. It consisted of securing the site and isolating and containing the waste
material. A locked, 8 foot high, chain-link barbed wire security fence was installed around the
perimeter of the three areas. A total of 252 visible capacitors were removed, as well as 20cubic
yards of stained soils. A 16 to 22 inch clay cap and a 6 inch topsoil cover were installed over the
main site.
The second phase of IRMs was specified in the CD. It began in late 1987 and was completed by
Westinghouse in 1988. The second phase included installing an additional area at the edge of
the main site, posting warning signs and removing sediment from Stout's Creek.
In September 1988, Viacom removed sediment along 1,600 feet of Stout's Creek. The creek was
hydrovacuumed from 25 feet upstream of the site to 500 feet downstream of the site. Sediment
was also removed from Stout's Creek 30 feet downstream and upstream of Hunter Road and
further downstream at Acuff Road.
The sediments were transported to the Interim Storage Facility at the Winston Thomas site or
storage. They were subsequently shipped by Viacom in early 1998 to a TSCA-pemmitted landfill in
Belleville, Michigan, for final disposal.
All lRMs that were implemented by Viacom were conducted with oversight and approval from the
CD parties. Maintenance of the site by Viacom began in 1985. Viacom personnel regularly
inspected the site to assure there was no disturbance of the site and to verify that the security
fences and cap remained intact.
1.2.4 1999 Remedial Action
In 1999 the site was further delineated and remediated according to the August 6, 1999,
"Remedial Action Work Plan, Bennett's Dump, Monroe County, Indiana", (Reference 9), which
was approved by the CD parties.
The remediation was performed to satisfy the requirements of the SOW for removal of soils and
wastes containing concentrations greater than or equal to 50 ppm PCBs with an average
concentration across the excavation that does not exceed 25 ppm. The excavation was
backfilled with a minimum of 12 inches of clean cover, graded to drain, and vegetated.
Site activities began in mid-August 1999, and were completed in early November 1999. The
project involved:
- Shipping a total of 36,157 tons of TSCA material to the Environmental Quality Company's
Wayne Disposal Landfill.
- Shipping a total of 1,756 capacitors weighing 118.72 tons to Onyx Environmental in Port
Arthur, Texas for incineration.
- The arithmetic average of all residual confirmation sample results was 11.3 ppm compared
to the 25 ppm requirement of the SOW.
- The site was backfilled with approximately 25,000 cubic yards of clean clay, graded for
drainage and seeded.
At three locations the excavation revealed deep quarry pits filled with rubble. The rubble
consisted of large boulders and smaller broken pieces of stone mixed with soil. At these
locations, capacitor parts and PCB contaminated soils existed above the rubble. The capacitor
parts and PCB soils were removed. Boulders and nubble were removed to the full reach of the
excavator at 17 to 20 feet deep. Each of these excavations filled with Groundwater in contact
with the rubble. The groundwater had a light oil sheen in some locations. An oil sample was
analyzed as being diesel fuel contaminated with PCBs. The water/oil mix was pumped and
treated to allow the excavations to proceed.
Samples were taken of dirt at the bottom of the excavations that probably sifted down from
above as the boulders were removed. Each of these areas produced sample results from the
bottom of the excavation that exceeded the SOW allowable limit of 50 ppm. The locations and
sample results of the subgrids that exceed the 50 ppm limit are:
H7-Center (east) & H7-NE 1 100 8 170 ppm
F6-SW 51 ppm
GO-NE 67 ppm
The CD parties allowed Viacom to temminate excavation in each section after removing as much
material as possible and collecting a final bottom grab sample. The average PCB concentration
for all of grid H7 is 122 ppm, for grid F6 is 25.3 ppm, and for grid G8 is 33 ppm. The subgrid
locations and sample results are shown on Figure 3.
The satellite area presented a similar situation. A pit encompassing portions of grids S2 and S8
was discovered that was filled with capacitor carcasses, capacitor parts and large amounts of
ash. The capacitors, and the soil and ash containing the capacitor parts were removed to a
depth of about 13 feet. Capacitors, capacitor parts and stained soils were chased and
excavated out of the sidewalls in all directions. Sidewall samples were taken until the cleanup
criteria was met in the north, east and south directions. The west sidewall of the satellite area
was removed down to a depth of 7 feet below grade and 10 feet westward into the road to a
point where all capacitors, capacitor parts, ash and soil were removed from the excavation. The
bottom and western sidewall consisted of only large boulders and rock debris all the way up to
the gravel roadbed. No appreciable soil or ash remained. The CD parties concurred that no
further sampling or excavation was warranted in this area. Figure 4 shows that the final
configuration of the bum pit excavation extended across grids S2, S8, S3 and S7.
The remedial action is documented in the "Final Report - Completion of Removal Action for
Bennett's Dump, CBS Corp, Febnuary 7, 2000", (Reference 10).
1.2.5 Interim Groundwater Monitoring Program
The SOW for the 1999 remedial action at Bennett's Dump called for an Interim Groundwater
Monitoring Program. Prior to the start of excavation activities and every 60 days during
remediation, the following locations were to be sampled:
South line of seeps
North Spring at culvert under tracks
MW-61
MW-6D
MW-3
Due to the dry conditions during the remediation in the summer and fall of 1999, the seeps and
springs were not flowing. It was agreed to add samples from Stout's Creek, upstream and
downstream of the site. Also, a sample was to be taken from the West Branch entrance to
Stout's Creek as shown in Figure 5.
The SOW also called for the implementation of a Long-term Groundwater Monitoring Program.
The Interim Groundwater Monitoring Program was to continue on a quarterly basis until the
Long-temm Groundwater Monitoring Program was approved and implemented.
In February and March of 2000 the Middle Spring and the Mound Spring, as shown on Figure 5,
were added to the interim monitoring program.
The results of the Interim Groundwater Monitoring Program are discussed in Section 1.6 and
listed in Table 1.
1.2.6 ~ 2000 Stout's Creek Bank Soil Removal
On May 15, 2000, Viacom characterized the PCB contamination in the sediments in Stout's
Creek and of the surface soils on the east bank of Stout's Creek. Based on the sampling
results, no creek sediments had to be removed, and only certain areas of bank soils were
removed. The objective of the remedial work plan was to clean up the bank soil for three
50 foot creek sections with sample results > 2.0 ppm. The three segments, as shown on
Figure 6, are Segment 6 with 2.7 ppm, Segment 9 with 2.4 ppm and Segment 13 with 2.0ppm.
On September 8 and 9, a depth of at least one inch of soil was removed for a width of about six
feet along each of these 50 foot lengths. This material was consolidated on the Bennett's Dump
site in Grid G8, as shown in Figure 3. The consolidated material was capped with at least one
foot of clean clay backfill.
1.3 Summary of Site Conditions
As detailed above, contaminated fill and soil were removed from the site. The excavations were
backfilled with clean clay from Conard's farm and revegetated. Sediments with PCB content
over 2 ppm were removed from the bank of Stout's Creek. Sediments in Stout's Creek adjacent
to the site were all found to be less than 2 ppm.
Star Stone Company is the present owner of the site. The site is currently inactive and not
occupied by any permanent workforce or residents. No long term use of the land has been
indicated by Star Stone. The site will likely remain inactive for at least the next few years except
for the presence of Star Stone employees working in other parts of the quarry.
Viacom has proposed the appropriate deed restriction for the site to USEPA and IDEM, but they
are not in place. Viacom has continued to maintain the site.
Viacom performed erosion repair work at Bennett's Dump during the week of September 5,
2000. A diversion berm was installed below the groveled parking area to prevent further
erosion. Areas were graded to prevent pending. Filled areas, which had sunk over the winter,
were refilled to grade. Hydroseeding and mulching of the regraded areas are incomplete and
will be done this season as weather permits.
Interim Groundwater monitoring is continuing on a quarterly basis.
1.4 Geology and Hydrogeology Summary
The geology and hydrogeology of the Bennett's Dump site was studied in the late 1980s. The
investigation plan is contained in the "Supplemental Hydrogeologic Investigation Plan (SHIP),
Winston Thomas and Bennett's Dump, Blasland and Bouck Engineers, P.C., August 1986.,
(Reference 11). The results of that investigation are presented in the report "Onsite Ground
Water Monitoring Plan - Bennett's Dump, B&B, May 1989", (Reference 3). A brief summary of
the findings of that investigation are presented here.
1.4.1 Site Geology
The geology of Bennett's Dump is characterized by a relatively thin layer of unconsolidated
material overlying bedrock. The unconsolidated material at the site consists of fill material and
indigenous soil. Fill materials range in thickness from 4 to 11 feet and generally consisted of
black to brown clay, sand, and gravel with rubble, brick, glass, and porcelain. As indicated in
section 1.2.4, in 1999 a total of 36,157 tons of contaminated fill were removed and replaced with
25,000 cubic yards of clay from the Conard farm.
Very compact gravel used as ballast for the old railroad bed was encountered in the upper three
feet of unconsolidated material in the western portion of the site, along Stout's Creek. This
gravel fill ranged in thickness from 1.4 to 3 feet. Other fill materials consisting of a mixture of
clay, limestone, and coal were encountered to the southern boundary of the main fill area. The
predominant soil encountered at the site is a yellow/red/brown, stiff silty clay that ranges in
thickness from approximately 2.5 to 5.5 feet. This silty clay grades with a red/gray, stiff clayey
silt that ranges in thickness from 1.6 to 4 feet. The area around the site contains large surface
and subsurface limestone quarry blocks, which were abandoned during quarry operations.
The Crider silt loam (CrC) is found north of the main Bennett's Dump site beneath a planted
field. This soil consists of silt to a silty clay loam. Permeability values are reported to range
from 0.6 to 2 inches per hour. Bedrock beneath this soil is usually encountered at a depth of
approximately five feet (Reference 4).
The bedrock unit present in the study area of Bennett's Dump is the Mississipian Age Salem
Limestone of the Sanders Group. The St. Louis and Ste. Genevieve Limestone of the Blue
River Group overlie the Salem Limestone and outcrop at elevations higher than the Bennett's
Dump study area. The Harrodsburg Limestone and Ramp Creek Formation of the Lower
Sanders Group underlie the Salem Limestone and outcrop at lower elevations near the site.
Regionally, the bedrock dips in a southwest direction at approximately 30 feet per mile;
however, local deviations may occur.
The Salem Limestone is the first bedrock unit beneath the site ranging from 90 to 100 feet in
thickness (References 5, 6). This limestone unit is composed of three lithologies: a light colored
limestone that is quarried for dimension stone, a similar limestone not used as dimension stone,
and impure limestone (References 5, 6). A gradational contact separates the Salem Limestone
from the underlying Harrodsburg Limestone; however, in some places in Monroe County, a few
feet of shale is present at the base of the Salem Limestone (References 5, 6). This shale may
provide a marker bed to distinguish between the Salem and Harrodsburg Limestone.
As indicated in the Supplemental Hydrogeologic Investigation Plan (SHIP), five borings which
ultimately became monitoring wells were installed in 1987 to provide compositional data on the
unconsolidated material (soil and silt) and lithological and structural infommation on the bedrock
at the site. Continuous core sampling of the unconsolidated material and the bedrock was
performed from the ground surface to an average depth of 42 feet at five locations (Wells MW-1,
MW-2, MW-3, MW-4 and MW-6D as shown in Figure 2).
The average thickness of the rock cored was approximately 35 feet. No significant stratigraphic
changes could be correlated and no useful marker beds were identified in the cores examined
from the site.
Weathered and fragmented limestone was encountered during the installation of wells MW-1,
MW-2, MW-4, and MW-6D. Gray/black shale less than 3 feet thick was encountered during the
installation of wells MW-3 and MOWED. This shale may represent the Somerset Shale member
that separates the Salem Limestone from the underlying Harrodsburg Limestone. Honeycomb
weathering was noted in the cores obtained at the locations of wells MW-1, MW-4, and MW-6D.
Horizontal and vertical fractures were noted in some of the bedrock core samples. Most of the
fractures were filled with either calcite or mud. Few enlarged solution features were noted in the
cores collected at the site. The deeper bedrock is composed of finer-grain calcite particles.
Packer tests perfommed during well installation indicated that these fractures did not transmit
water. The subsurface logs for the borings/corings are provided in Appendix 2 of Reference 3.
The test borings and rock corings were performed during the months of June, July, August and
October of 1987.
At the completion of the boring/coring and well installation activities at the locations of wells
MW-1, MW-2, MW-3 and MW-4, the coreholes/wells were caliper logged and gamma-ray
logged. No geophysical logging was conducted at wells MW~I and MW-5. No large voids were
measured in the wells that were caliper logged. In general, only small changes (~0.5 inches) in
the well diameter were measured in the wells logged.
Because of the lack of information on the connection of the wells to any major water bearing
conduits, video logging was conducted in 1993. Unfortunately, heavy corrosion of the surface
casing in the open-hole wells had occurred, which resulted in rust flakes that partially obscured
the camera view. Nevertheless, solution conduits about an inch or so in diameter could be
noted in several wells just below where the surface casing was seated into bedrock, and within
the first 10 to 15 feet of bedrock. This also coincides with packer test results that indicate the
lower part of the wells to be less transmissive. Therefore, no major conduit connections to any
of the existing monitoring wells were discovered.
The details of the monitoring well construction are shown in Table 2 (Part 2). Well locations are
indicated on Figure 2. Water elevations measured in the monitoring wells are shown on
Table 3.
1.4.2 Site Hydrogeology
The Groundwater flow system associated with the site is composed of recharge areas, flow
areas, and discharge areas. Recharge to the Groundwater flow system occurs in the
topographically higher areas east and south of the site through open water-filled quarries (pits)
and through old quarries that have been backfilled with rubble. Although surface water runoff is
a contributing source of water to the quarries, the predominant origin of the water in the quarries
is believed to be Groundwater.
Groundwater from the Bennett's Dump site is believed to primarily discharge to Stout's Creek.
Based on the Groundwater elevation data collected from the monitoring wells in August and
November 1987, and March, June, September and December 1988, Groundwater flow is
generally to the west-northwest towards Stout Creek for all measurement periods (see Figures
5A through 5F of Reference 3). In the southern portion of the site, the groundwater flow
direction trends more directly west toward Stout's Creek. In the central and northern areas of
the site, the groundwater flow direction trends west-northwest toward Stout's Creek. Horizontal
groundwater gradients varied from approximately 0.05 feet/foot to 0.03 feet/foot in the southern
portion of the site and from approximately 0.03 feet/foot to 0.02 feet/foot in the central and
northern portions of the site.
The Salem Limestone and the unconsolidated deposits are integrated to comprise one
hydrogeologic system. The depth to groundwater at the site ranges from about 2.5 to 14 feet
below ground surface. The groundwater flow in the bedrock occurs in solution enlarged joints
and fractures. Several seeps located within the limit of the main fill area at the site may also be
local groundwater discharge points.
1.5 Topography and Surface Water Features
Bennett's Dump is located along the eastern margin of the Mitchell Plain physiographic region.
This region is characterized by relatively flat topography with moderate slopes. The topography
near the site is characterized by numerous rectangular water-filled pits (quarries) left from the
quarry operations. A large water filled pit referred to as the Icebox Quarry exists about
100 yards directly east of the northern section of the site. Several other quarry pits exist to the
east, southeast and southwest of the site. Many old quarry pits in the area had been filled with
rock rubble during the past quarrying operations.
INDOT is currently building a highway within a mile south and southeast of the site. As part of
this construction, some of the water filled quarries were filled during the year 2000. The water in
the quarries was not removed as the quarries were filled. This may have temporarily raised the
groundwater elevations in the area.
The main area of the site is on a gently westward sloping hillside east of Stout's Creek.
Elevations at the site range between 710 and 750 feet above mean sea level. To the south of
the site, two streams join forming Stout's Creek, which flows north from the site area. Stout's
Creek is joined just north of the site, from the west by the stream referred to as the West
Branch, as shown in Figure 5.
There are four springs within the Bennett's Dump site that have been sampled as part of the
Bennett's Dump Interim Groundwater Monitoring Program. Two perennial springs at the site,
the Middle Spring and the Mound Spring are within the main excavated area. These two
springs emerge from within the excavated and backfilled area and run into Stout's Creek. Two
other intermittent springs on the perimeter of the excavated area are the North Spring and Mid-
north Spring. A 24 inch culvert exists at the North Spring and drains under the rail road tracks
to Stout's Creek. The locations of these springs and the culvert are shown on Figure 5. North
Spring has not been observed flowing since before the remedial action excavation.
The on-scene coordinator's report from 1983, discussed in Section 1.2.1, describes:
1. A small pond, possibly a spring, on the eastside of the fill.
2. An adjoining pond draining west toward Stout's Creek.
3. A small pond along the west border of the site, situated between
the fill and the railroad tracks. This small pond flowed via two
routes directly into Stout's Creek.
The report contains a site plan that shows that the first pond on the east side of the fill
corresponds to the Mound Spring currently being sampled in the interim monitoring program.
The third spring along the west corresponds to the Middle Spring, which is also being sampled
as part a! the interim monitoring program.
There are also several wet weather springs that are visible flowing to Stout's Creek from north
and west of the middle spring during and after rain events.
1.6 Historical PCB Data
1.6.1 Groundwater Monitoring Well Samples
Groundwater monitoring wells in karst terrain are of highly questionable use and difficult to
interpret. This is because most of the Groundwater in karst moves in discrete conduits. Unless
the well just happens to intercept one of these conduits, the data from the well cannot be used
as an overall indicator of groundwater quality at the site or the transport of contaminants from
the site. The experience of Viacom and the general industry is that attempting to locate
conduits in karst and intercept them with monitoring wells is an extremely difficult and uncertain
task. Short of this effort, the value of monitoring well data both past and future is highly
questionable.
The EPA has recognized this situation. EPA guidance for groundwater monitoring in karst is
contained in "Groundwater Monitoring in Karst Terrain: Recommended Protocols and Implicit
Assumptions", (Reference 7), and "RCRA Ground-Water Monitoring Technical Enforcement
Guidance Document", (Reference 8). These documents state that the proper locations for
monitoring the status of Groundwater in karst areas are springs, cave streams and monitoring
wells that have been proven by dye tracing to intercept conduits carrying water from the
monitored location.
As discussed in section 1.4.1, seven monitoring wells were installed at the Bennett's Dump site in
1987 and 1988, as shown on Figure 2. Six of the wells surrounded the main fill area of Bennett's
Dump where capacitors were known to exist. Four of the wells were positioned between the main
fill area and the adjacent Stout's Creek. One well, MW-44 , was located in a small satellite area to
the north of the main site, which has since been evaluated as not containing any PCB
contamination. MW-4 was abandoned during the remedial action in early August 1999, along with
MW-2, which was abandoned to allow access to the site.
The monitoring wells were sampled quarterly during 1988 for PCBs. Additional PCB samples
were taken from the monitoring wells since 1999 for the Interim Groundwater Monitoring
Program.
During 1988, PCBs were detected during each of the four quarterly sampling events in wells MV\t
61 and MW-6D, and once in well MW-3. The maximum total PCB concentration detected in
Groundwater was 27.3 ug/L for MW-6I. The use of well MW-5 was discontinued in March 1988 due
to the presence of free PCB product within the well. The sample analytical results are included in
Table 4.
From August 25, 1999 until present, monitoring wells MW-3, MW-6I and MW-6D have been
sampled for PCBs nine times under the interim monitoring program. These interim sample
results are listed in Table 1. MW-3 has been consistently BDL. MW-1 results were up to 1.2
ppb.
MW-6D was sampled at 58 ppb on August 25, 1999, before remediation. A field duplicate
sample of MW-6D, taken and analyzed at the same time was reported as 2.6 ppb. The samples
were visibly different, with the 58 ppb sample reported to contain a larger amount of sediment.
It was concluded that field conditions were not stable during the time that these duplicate
samples were obtained. The validation report on these duplicate sample results calls for this
data to be flagged as estimates only. The sample results since for MW-6D have been between
5.9 and 15 ppb.
Also, since November 1999, all sample results for well MW-6D have identified Aroclor 1221 as
the main constituent. Straight Aroclor 1221 was not used by Westinghouse in capacitors and
this Aroclor is not seen in the Stout's Creek downstream samples. It is not clear how to interpret
the appearance of this Aroclor at the site.
The boring logs, packer tests, caliper logs and gamma-ray logs from the installation of these
Bennett's Dump monitoring wells, as discussed in Section 1.4.1, indicate that none of the
Bennett's Dump wells intercepted major Groundwater conduits.
1.6.1.1 Investigation of DNAPL in MW-5
In September 2001, Viacom assessed the presence of PCB free product as a DNAPL in MW-5.
On September 5, a bailer sample was pulled from the well. Contained in this sample was a
mixture of globules of free phase product, sediment and water. This has previously been
mistakenly identified as 9" of pure product. On September 6, several bailer samples were
pulled from the well. There appeared to be about 1" of globules of free phase product mixed
with sediment and water in each bail. The bailer also had an oily coating on the outside. On
September 9, an oil-water interface probe was lowered into the well and failed to detect a
separate phase at the bottom of the well. Flexible aluminum tubing was inserted into the well
near the bottom. On October 15, 2001, the tubing was connected to a peristaltic pump and a
sample volume of 2.25 gallons was removed from the bottom of the well. This sample consisted
of globules of free phase product, sediment and water.
1.6.2 Surface Water
Stout's Creek is the main surface water body associated with the site. All known springs and
surface water stomm drains eventually flow into Stout's Creek. Open quarry pits in the area
collect some surface water and Groundwater. This water from the quarry pits also flows via
fractures and conduits to Stout's Creek. Water was sampled by the USEPA on April 17, 2001 in
the Ice Box Quarry at 0.21 ug/L and the in the Wedge Quarry at <0.10 ug/L.
1.6.2.1 Stouts Creek Surface Water Sampling
Surface water samples have been collected in Stout's Creek on several occasions since 1993.
In July 1993, two surface water samples were collected from Stout's Creek, one upstream of
Bennett's Dump and the other downstream. PCBs were not detected in the upstream sample (at a
it appears that the springs present within the site transport most of the site groundwater to the
creek.
1.6.2.3 April 1998 Storm Event Sampling
Stout's Creek water was sampled during a stone event on April 15, 1998. Two inches of rain
fell during this stomm event which produced water levels of three feet in Stout's Creek at the
gauging station upstream of the West Branch entrance. Over 50 surface water samples were
collected by auto-samplers at three locations in Stout's Creek under high flow conditions.
Sample locations in Stout's Creek were upstream of the site, downstream of the site at Hunter
Road and in the West Branch entrance to Stout's Creek. Figure 7 shows the PCB concentration
and water flow versus time during the storm event. PCB content of the water upstream of the
site was typically BDL before the stomm. As the flow in Stout's Creek increased, the PCB
content in the water upstream of the site consistently rose to between 0.1 and 0.3 ppb until the
storm flow peaked. On the receding limb of the stomm event, the PCB content of the upstream
samples resumed to BDL.
The PCB content of the Stout's Creek downstream water samples during the storm event
started out at levels typical of the low flow data. Figure 7 shows that during the rising limb of the
storm the downstream PCB levels stayed about the same as the upstream PCB levels rose.
This could be explained by a lag in the flow increase of the springs compared to the flow
increase in the stream during the stomm. Previous surface water monitoring has shown that the
springs have higher PCB content but lower flow rates than Stout's Creek, especially during
storm conditions. The downstream Stout's Creek flow is a combination of the upstream creek
flow and the spring flows that enter the creek from the site. As the creek flow increases during
the storm, the effect of the spring flows into the creek become insignificant until the spring flow
rates also increase.
Figure 7 shows that on the receding limb of the creek flow curve, as the creek flow decreases,
the PCB level in the downstream samples stays about the came or increaser. even though the
PCB level of the water upstream of the site has resumed to BDL. During the period of the
receding limb of the storm, the flow from the springs may have increased. Since the springs
have a much higher PCB content than the water coming from upstream in Stout's Creek, the
spring flows are most likely causing the downstream PCB levels in Stout's Creek to remain high.
The downstream PCB levels in Stout's Creek become non-detectable late on the receding limb
most likely because flow in the springs recedes and the much higher flow of clean water from
upstream dilutes the spring flows.
1.6.3 Sediment Sampling
Table 6 presents a summary of the sediment samples taken from Stout's Creek from 1988 until
1993. In early 1988, Viacom removed sediment along 1600 feet of Stout's Creek.
In July and August 1988 and July 1993, sediment samples were collected from Stout's Creek along
Bennett's Dump. PCBs were not detected (at a detection limit of 1.0 mg/kg) in any of the samples.
In April and May 1998 sediment and fish samples were taken under low flow conditions in Stout's Creek. In all, 28 sediment samples were taken from just upstream of the site to just
upstream of the confluence with Bean Blossom Creek. Two sediment samples were taken in
the West Branch of Stout's Creek just upstream of the confluence with the east branch.
Sediment samples were taken at 100 foot spacing from Hunter Road south to the site boundary,
then at 50 foot spacing to an area adjacent to MW-6, then at 100 foot spacing again to the
southern site boundary. A sample was also taken further downstream at Acuff Road and just
upstream of the confluence with Bean Blossom Creek. Figures 8 and 9 show the sediment and
water sample locations. All samples were grab samples taken from the approximate center of
the stream or in the most abundant sediment pool at that location. Sediment sample results
varied from less than 0.1 ppm to 3.2 ppm as shown in Table 7. Generally, only samples
downstream of the middle spring and upstream of the West Branch confluence with Stout's
Creek showed PCBs greater than 1 ppm.
On June 27 and 28, 2000, sediment samples were taken in accordance with the approved
May 15, 2000 Work Plan. Fourteen 50 foot lengths along the creek were sampled for both
creek sediments and bank soils as shown in Figure 6. For each 50 foot length, five creek
sediments were compositedand five bank soil samples were composited. Individual sample
aliquots were taken approximately every 10 feet along the 50 foot length.
Creek sediment samples were taken from under water within the creek. Bank soil samples
were taken at an elevation of about one half to two feet above the water level of the creek.
The sample results are tabulated in Table 8. Three of fourteen creek sediment samples were
above 1.0 ppm PCB. The highest value was 1.7 ppm for Segment 7. The average of all
fourteen creek sediment samples taken was 0.64 ppm. Six of fourteen bank soil samples were
above 1.0 ppm. The highest bank soil result was 2.7 ppm for Segment 6. The average of all
fourteen~bank soil samples taken was 1.05 ppm.
Based on the June 2000 sampling results, no creek sediments were removed, and only certain
areas of bank soils were removed. The objective of the remedial work was to clean up the bank
soil for the three creek sections with sample results > 2.0. The three segments, as shown on
Figure 6 are Segment 6 with 2.7 ppm, Segment 9 with 2.4 ppm and Segment 13 with 2.0 ppm.
A depth of at least one inch of soil was removed for a width of about six feet along each of these
50 foot lengths. This material was consolidated on the Bennett's Dump site in Grid G8 and
capped with at least one foot of clean clay backfill.
1.6.4 Fish Sampling
Fish have been collected in Stout's Creek on four occasions beginning in 1983. Tables 10 and
11 present all the fish data collected in Stout's Creek. Table 11 lists the historical fish data from
Stout's Creek from 1983 to 1992. Figure 11 presents a comparison of historical creek chub
data at the Acuff Road location. Fish at this location were much more contaminated prior to the
interim measures taken at the site. Forty-eight fish samples were collected from 3 locations
downstream of the site in May 1998. Table 11 tabulates this data. Figure 12 presents the 1998
data as averages for all whole body samples at each of the three stations sampled. The data
shows a steady decline of PCB levels in fish with distance downstream away from the site.
1.6.5 Residential Wells
Indiana University collected water samples from 66 residential wells located within a 5,000 feet
radius of Bennett's Dump in 1986 per the CD requirements. PCBs were not detected in any of the
wells at concentrations greater than the drinking water standard (MCL) of 0.5 ug/L. Seven of the
residential well samples contained detectable levels of PCBs, above the detection limit of
0.001 ug/L. Table 9 lists the residential well sample results.
As shown in Table 9, one residential well at 4005 Woodyard Road had PCB levels at 0.407ug/L.
This value approaches the MCL of 0.5 ug/L. This well was disabled and the residents now use
only city water. Table 9 shows six other wells with detectable PCB levels between 0.002 and
0.007 ug/L, which are well below the MCL. It is not known if the source of the PCBs in the well at
4005 Woodyard Road was Bennett's Dump or some other location.
IDEM and Monroe County performed additional residential well sampling in 1988. Three Stout's
Creek samples were taken at the same time. Seven residential wells were sampled and all found
to be non-detect (<0.1 ug/L). Table 9A lists the results of the residential well and Stout's Creek
water samples taken in 1988. This sampling included one of the seven residential wells which had
detectable PCB levels in 1986. Viacom took split samples at four of the wells. Three samples
were analyzed at non-detect (<0.1 ug/L) and one sample was lost due to an extraction error.
2.0 ~ Long-term Monitoring Approach
The CD contains provisions and requirements for the long-term groundwater monitoring at the
Bennett's Dump site. This plan was based on the model of porous media flow and required a
suite of onsite and offsite wells. This model is not appropriate for this karst site. Therefore the
original groundwater monitoring provisions were deleted by consensus of all the CD parties.
The SOW for the site negotiated in 1999 required the implementation of an Interim Groundwater
Monitoring Program as discussed in section 1.2.5. The SOW also requires the submittal of a
Long-term Groundwater Monitoring Plan by Viacom. The purpose of the long term monitoring
plan as stated in the SOW is to determine that the remedy is functioning as set forth in the
amended ROD. A review of this monitoring plan and data will occur in August 2004, at which
time the CD parties will decide if the prescribed monitoring will be maintained, reduced or
eliminated. Also, during the base monitoring period, changes to the plan may be proposed and
the plan changed with the consent of all the parties.
A review of the site history, hydrogeology and historical PCB data shows that:
- The remediation of the site in 1999 was substantial and met the intent of the original CD, the
SOW and amended ROD. A total of 36,157 tons of TSCA material were removed and
disposed offsite. The final site average for the remediated area is 11.3 ppm.
- PCB contaminated light oils were found within the rock in buried quarries at the site. These
oil/water mixes were pumped out but some residuals remain in contact with groundwater in
these areas.
- The site is located on the Mitchell Plain karst terrain. Stout's Creek is the regional
groundwater sink in the area with all upper level water bearing zones at the site appearing to
discharge to the creek. The most accurate indicator of groundwater conditions will be
springs and/or stream water samples.
- There are two main springs at the site and several smaller seeps that appear only in wet
weather. The two main springs have been sampled and have PCB contamination. These
springs enter Stout's Creek at the location where the past sediment contamination in the
Creek has been the highest.
- The existing wells were installed randomly with respect to karst features and have not been
detemmined to be in contact with major groundwater flow paths.
- There still remains an undetermined amount of free phase product at the bottom of MW-5
mixed with sediment. Over the time period of the September 2001 examination, free phase
product did not appear to increase.
Based on the above and the SOW goals, the groundwater monitoring plan should be structured
to primarily monitor site springs and the water of Stout's Creek. The springs and the creek
naturally integrate the groundwater from a broader area and provide a more comprehensive
view of the status of groundwater and contaminant transport at the site.
The two perennial springs at the site within the main excavated area are the Middle Spring and
the Mound Spring as shown on Figure 5. These two springs emerge from within the excavated
and backfilled area and run into Stout's Creek. Viacom is currently sampling these springs as
part of the Interim Groundwater Monitoring Program.
Although it is not clear how data obtained from monitoring wells MW-61 and MW-6D will be used
to better understand Groundwater at the site, at the request of the government parties, Viacom
has agreed to monitor these two wells for PCBs semi-annually until the end of the review period.
Viacom has also agreed to remove the free product and sediment from MW-5 and observe if
free product returns.
2.1 Long-term Monitoring Details
The Long-term Monitoring Plan shall include:
- Sampling of the two perennial springs, the Middle Spring and the Mound Spring, will be
done quarterly. for PCBs until the end of the review period. Flow measuring, datalogging weirs
are being installed at Middle Spring and Mound Spring to obtain continuous flow data for these
two springs. The spring flows will be monitored continuously for one year. At that time the flow
data will be reviewed and a decision will be made by the CD parties on extending the
- Sampling of any other spring onsite that is flowing will be done quarterly for PCBs. For
the long-term sampling of these springs, a qualitative and /or quantitative estimate of spring flow
will be made, if possible, when the sample is taken.
Figure 5 shows the Mid-north Spring and North Spring, which are intermittent springs on site
and which will be sampled quarterly when they are flowing. Efforts will be made to sample the
intermittent springs during times when the intermittent springs would be flowing, such as after
significant rainfalls or during wet periods. A flow-measuring weir will be installed at Mid-north
Spring to provide manual flow readings.
- Quarterly low flow PCB sampling of Stout's Creek water will be done at locations
immediately upstream and downstream of the site. The upstream sample will be taken at the
same location used for the interim monitoring as shown on Figure 5. The downstream sample
will be taken just upstream of the West Branch entrance to Stout's Creek. A datalogging
gauging station will be located at this location to continuously estimate the creek flow. Specific
flow measurements will be recorded at the time the water samples are obtained. These two
samples will provide an indication of any significant PCB transport to Stout's Creek from any
bank seeps or springs.
Sampling of the springs and the creek will be done at the same time so that data can be
correlated. Temperature and conductivity data will also be recorded for these samples.
- Annual high flow sampling events of Stout's Creek will be planned for the receding limb
of a major spring storm event. Data from the April 1998 storm event shows that the
downstream PCB samples are the highest during the receding limb. The same upstream and
downstream locations used for low flow monitoring discussed above will be sampled. The flow
in the creek will be measured continuously using a datalogger at the gauging station as shown
in Figure 5. PCB sampling and flow data logging will also be performed at the Middle Spring
and Mound spring during the storm event. Any other onsite springs flowing during the storm
event will also be sampled. Estimates of these flows will be made when the water samples are
taken.
- Near the end of the monitoring period, in 2003, fish and sediment will be sampled in
Stout's Creek. Fish and sediments will be sampled in the same locations as sampled in 1998.
- Monitoring wells MW-61 and MW-6D will be sampled for PCB analysis semi-annually.
Water elevations, temperature, conductivity, pH and turbidity data will also be measured for
these samples. The monitoring well samples will be taken during every other sampling event for
spring and stream samples so that data can be correlated.
- MW-5 will be purged of PCBs and then observed quarterly for one year to detemmine if
free product returns. See 2.1.1 and 2.1.2, below for further discussion of MW-5.
2.1.1 MW-5 Purging Procedure
Viacom will use a jet pump modified for deep well pumping to remove sediment and free
product from the well according to the following procedure:
- Measure depth to water and depth to bottom.
- Calculate one well volume
- Using jet pump, remove sediment and water in well.
- Let well recover and repeat procedure until 5 volumes are purged.
- All purge material will be discharged into dedicated 5-gallon carboys and disposed of in
an approved manner.
- Allow well to settle overnight and measure depth to bottom.
- Repeat purge if any measurable sediment remains in well.
- Allow well to sit undisturbed for a week.
- Then slowly lower a dedicated 2" bailer to the bottom of the well. Slowly withdraw the
bailer and observe the contents. Especially note if any globules of oil or free phase
product is evident.
- If the bailer sample shows no evidence of any free phase product, then commence the
quarterly observations of the well a
s described below. If free phase product is visible,
consider alternate cleanout plans.
2.1.2 Quarterly Observation of MW-5
Quarterly observation for one year of MW-5 will take place using a dedicated 2" diameter clear
plastic bailer after the well is cleaned out as described in 2.1. 1. A depth to water and depth to
bottom measurement will be taken. The bailer will be slowly lowered into the well to the bottom
and slowly withdrawn. A description will be recorded of the contents of the bailer.
If after one year of quarterly observations of MW-5, no additional free product is observed in the
well, then observation will continue on a semi-annual basis. If free product is observed to be
accumulating in the well at the end of the first year, Viacom will submit a plan for further
assessing the well. If at the end of the base monitoring period no additional free product has
accumulated in MW-5, then Viacom will submit a closure and abandonment plan for the well.
3.0 Data Analysis and Reporting
Long-term monitoring at Bennett's Dump will be done until the end of the review period. The
Long-term Monitoring Plan sample points will be sampled until August of 2004. Quarterly
reports of the data will be presented to the CD parties during the base monitoring period.
Viacom will work with the parties to develop a process to provide stage and flow data, water
level data and water quality data in an electronic format.
At the end of the five year period, the CD parties will evaluate all the monitoring data and decide
if monitoring will cease, continue as is, or continue in a modified form.
4.0 Sample Collection
For creek surface water and springs at non-storm conditions, an unfiltered grab sample will be
taken by hand dipping a ~ liter bottle into the main exit point of the spring orifice or centroid of the
stream flow as applicable. The samples will be sent for total PCBs and TSS analysis. The PCB
analysis will be to a detection level of 0.1 ppb to an approved lab for this project whose procedures
will be in accordance with the requirements of "Test Methods for Evaluation of Solid Waste:
Physical/Chemical Method" (EPA SW-846, latest edition) analytical method 8082. TSS samples
will also be sent to an approved lab and analyzed in accordance with procedures that meet the
requirements of EPA 160.1 from EPA 600/4-79-030 latest edition.
During each sample cycle, a duplicate sample and field blank will also be taken. The duplicatewill
be a second sample of water taken from one of the sample points. The field blank will be an
identical sample bottle filled with Dl water at the site while taking the samples. During barnstorm
conditions field parameters of conductivity and temperature will also be measured.
During storm conditions, samples may be taken with an ISCO auto sampler. Each sample will be
approximately 500 ml and taken into a glass container in the base of the sampler on an hourly
basis until 10 hours after the peak flow and then the frequency will be decreased if determined by
the sampling crew to be appropriate. When auto samplers are used to collect stomm samples, the
sampler will be iced. The maximum amount of time that a sample can be left in the sampler
before it is removed, sealed and refrigerated will be limited to 12to 16 hours.
Well samples will be taken with dedicated tubing and a peristaltic pump following low purge
techniques. Field parameters of conductivity and turbidity will be used to detemmine when
conditions are stable. Conductivity will be stabilized within 10% and turbidity will be less than
5 NTU and stabilized within 20%.
5.0 Sample Custody Procedures
5.1 Sample Identification System
A sequential sample numbering system will be used to identifyeach sample, including duplicates
and blanks. Each sample will be assigned a unique sample number. The field activity leader will
maintain a listing of sample identification numbers in the field logbook. Each sample number will
consist of six digits as illustrated by the following example: BD0001.
The "BD" is the site code and refers to Bennett's Dump. The four digits are the sequential number.
The sample number will be added to the respective field notebook, sample label, and chain-of-
custody form.
5.2 Initiation of Field Custody Procedures
For all samples, Region V chain-of-custody protocols, as described in the UNational Enforcement
InvesEgabons Center (NEIC) Policies and Procedures, EPA-330/~DDI-R, Rev. June 1985"
(Reference 13), will be followed. Custody procedures are described in Section 5.0 of the QAPjP.
5.3 Field Activity Documentation and Logbook
A field logbook, as discussed in FP-1 of the QAPjP, will be initiated at the start of the Field
Sampling Program and maintained to record on site activities. The field logbook is a controlled
document that becomes part of the permanent site file. The field logbook will consist of a bound
notebook with consecutively numbered pages that cannot be removed. The logbook cover will
indicate the following:
- Project name
-
Project Geologist's and Field Activities Leader's name
- Sequential book number
- Project start date
- Project end
It is important that this document be maintained to provide a record of field activities. Daily end ies
will be made during periods of site activity. Entries will include the following:
- Summaries of daily site activities
- Arrival and departure of site visitors
- Arrival and departure of equipment
- Start and completion of sampling activities
- Sample pickup including chain-of-custody form number, carrier, date, and time
- Equipment calibration and repair
- Decontamination procedures used
- Health and safety issues
- Levels of personal protection
At the beginning of each entry, the date, start bme, weather conditions, and names of the site
personnel and visitors present will be recorded. Each page will be initialed. Enb ies will be
recorded in ink, and no erasures are pemmitted. Incorrect entries will be stricken with a single line,
initialed and dated.
Section 5.1.2 and FP-1 of the QAPjP on Field Logbook Record Keeping will be adhered to. In
addition to field logbooks, data sheets to record specific field parameters will also be used. Copies
of the data sheets will be included with all data transmittals and originals will be film in pemmanent
project records.
5.4 Sample Shipment and Transfer of Custody
Sample handling and shipping procedures and transfer of custody procedures are provided in
Section 5.0 and FP-12 of the QAPjP.
6.0 Sample Container Preparation, Sample Preservation, and Maximum
Holding Time
6.1 Bottle Requirements
The contaminant-free sample containers (bottles) used for this sampling effort will be prepared
according to the procedures specified in ~USEPASpecifications and Guidance for Obtaining
Contaminant-Free Sample Containers, December, 1992r, (Reference 12). Bottles used for the
sampling activity will not contain target organic and inorganic contaminants exceeding the level
specified in the above mentioned document. Specifications for the bottles will be verified by
checking the supplier's certified statement and analytical results for each bottle lot, and will be
documented on a continuing basis. This data will be maintained in the project evidence file and will
be available, if requested, for review by the government parties.
In addition, the data for field blanks, etc., will be monitored for contamination per Section 3.1 of the
QAPjP. Corrective actions will be taken as soon as a problem is identified and include
discontinuing the use of a specific bottle lot, contacffng the bottle supplier(s) for retesting the
representative bottle from a suspect lot, resampling the suspected samples, and validating the
data, taking into account that the contaminants could be introduced by the laboratory (i.e., common
lab solvents, sample handling artifacts, etc.). If a bottle QC problem occurs, a determination of
whether the bottles and data are still usable will be made.
Amber glass bottles with tenon liners will be used for PCB water samples.
6.2 Sample Preservation and Holding Time
Samples will be stored on ice to 4øC for preservation. Maximum holding times until extraction will
be seven days for water samples. Maximum holding times until analysis of extract from water
samples will be forty days.
6.3 Sample Handling, Packaging, and Shipment
Sample Handling and Transporting instructions are listed in Section 8.2.6 of F~3 for Groundwater
samples. Sample packing and transportation requirements are described in FP-12.
7.0 Decontamination Procedures
This section provides the general guidelines for the decontamination of sampling and monitoring
equipment and sample bottles. FP-2 of the QAPjP discusses decontamination procedures.
The following equipment will be on site:
- Distilled water
- 10 percent by volume isopropanol and water solution
- Non-phosphate detergent
-
Scrub brushes; squirt bottles for alcohol and water; plastic bags and sheets
- Drums or carboysfor disposal of waste
7.1 Sampling Equipment Decontamination
All sampling equipment and monitoring equipment (e.g. temperature and conductance probes) will
be decontaminated between sampling locations by the following procedures:
- Wash contaminated equipment contact surfaces with nonphosphate detergent.
- Rinse with tap water.
- Spray rinse with 10 percent alcohol solution.
- Rinse with distilled water and air dry.
7.2 Sample Bottle Decontamination
Sample bottles or containers filled in the field will tee decontaminated before being packed for
shipment or handled by personnel without dermal hand protection as follows:
1. Wipe container with a paper towel dampened with potable water.
2. Dispose of used paper towels as specified in the Section 9.
8.0 Preventive Maintenance Procedure and Schedule
Field team members will refer to the field procedures in the QAPjP or the manufacturers'
instrument manuals for the appropriate preventive maintenance procedures for the field equipment
used at the site. Section 11.0 of the QAPjP discusses Preventive Maintenance Procedures.
9.0 Investigation-Derived Waste
The waste material generated during a field investigation is known as Investigation Derived Waste
(IDW). At this site, there is a very low potential to generate IDWthat has any significant level of
contamination on it. This is because all high level contamination has been removed from the site.
9.1 Types of Investigation-Derived Waste
Materials that may become IDW requiring proper treatment, storage and disposal are:
Personnel protective equipment (PPE). This includes disposable coveralls, gloves, booties,
respirator canisters, etc. It is expected that nommal work clothes will be used by samplers
with disposable gloves and booties where appropriate.
Disposable equipment (DE). This includes plastic ground and equipment covers, aluminum
foil, Teflon tubing, broken or unused sample containers, sample container boxes, tape,
etc.
Groundwater obtained through well development or well purging.
Cleaning fluids such as spent solvent and wash water.
9.2 Management of Investigation-Derived Waste
In general there will be a small quantity of IDW generated during the sampling related to this plan.
Disposal booties and gloves should not be heavily contaminated and can be disposed of with
nommal site trash. Any spent hazardous cleaning liquids will be disposed of in accordance with
EPA regulations. Waste generated will be properly contained and labeled at the site. The waste
will be manifested and shipped to a pemmitted treatment or disposal facility in accordance with EPA
regulations. In the case of purge water, it will be taken to the Neal's Landfill Spring Treatment
Facility, for treatment and disposal.
10.0 Well Abandonment
Once the use of a monitoring well has ended and no further future use is contemplated, the well
will be abandoned in accordance with the Department of Natural Resource Regulations 312 IAC
13-10-2, following receipt of consent to do so from the government parties.
Section 2(e)(6) of 312 IAC 13-10-2 specifies that "A cased or uncased monitoring well shall be
plugged from the bottom of the well or borehole to the ground surface with a bentonite slurry or
pelletized or coarse grade crushed bentonite."
The Department of Natural Resource Regulations shall be notified in writing of the well
abandonment within thirty days after plugging is completed.
References
1. On-scene Coordinator's Report, USEPA, June 1983.
2. Consent Decree, Civil Action No. IP 83-9-C, USA and the State of Indiana v. Westinghouse
Electric Corporation and Monsanto Company, and Civil Action No. IP 81448-C, The city of
Bloomington and Monroe County, Indiana v. Westinghouse Electric Corporation and Monsanto
Company, entered August 1985.
3. Onsite Ground Water Monitoring Plan - Bennett's Dump, B&B, May 1989
(Reference 5-17)
4. U.S. Department of Agriculture, Soil Survey of Monroe County, Indiana, 1981
(Reference 16)
5. Nicoll, R. S., and C.B. Rexroad, ~Stratigraphy and Conodont Paleontology of the Sanders
Group (Mississippian) in Indiana and Adjacent Kentucky," Indiana Department of Natural
Resources, Geological Survey Bulletin 51,1975. (Reference 13)
6. Shaver, R. H., et. al.,WCompendium of Rock-Unit Stratigraphy in Indiana, Indiana
Department of Natural Resources, Geological Survey Bulletin 43, 1970 and revised second
edition, 1987. (Reference 19)
7. Ground-Water Monitoring in Karst Terranes: Recommended Protocols and
Implicit Assumptions, EPA 600/X-89/050, Feb 1989.
8. RCRA Ground-Water Monitoring Technical Enforcement Guidance Document,
OSWER-9950.1 November 1992.
9. Remedial Action Work Plan, Bennett's Dump, Monroe County, Indiana, CBS Carp,
August 6,1999
10. Final Report - Completion of Removal Action for Bennett's Dump, CBS Carp,
February 7, 2000.
11. Supplemental Hydrogeologic Investigation Plan (SHIP), Winston Thomas and
Bennett's Dump, Blasland and Bouck Engineers, P.C., August 1986.
12. USEPA Specifications and Guidance for Obtaining Contaminant-Free Sample
Containers, December, 1992.
13. National Enforcement Investigations Center (NEIC) Policies and Procedures, EPA-
330/~DDI-R, Rev. June 1985
|