IN THE UNITED STATES DISTRICT COURT
FOR THE SOUTHERN DISTRICT OF INDIANA
INDIANAPOLIS DIVISION
April 16, 2003 Sarah Elizabeth Frey,
et al.,
Plaintiffs,
v.
United States Environmental
Protection Agency, et al.,
EPA REPLY MEMORANDUM IN SUPPORT OF
UNITED STATES' MOTION FOR SUMMARY JUDGMENT
INTRODUCTION
Plaintiffs brought this action on April 20, 2000, seeking to
challenge various aspects of the environmental cleanups at three
related hazardous waste sites in the Bloomington, Indiana, area:
the Lemon Lane Landfill, Neal's Landfill, and Bennett's Dump.
Plaintiffs amended their complaint on March 4, 2003, and recast
some of their allegations but did not add any new claims. The
United States has moved for summary judgment, arguing that
because the remedial actions have not yet been completed at any
of these sites, Plaintiffs' claims are barred by CERCLA section
113(h), 42 U.S.C. # 9613(h), and the United States is entitled to
judgment as a matter of law.
Plaintiffs' opposition to summary judgment contains several
inaccuracies and misstatements, but one fundamental flaw pervades
Plaintiffs' argument. Plaintiffs assert that section 113(h) only
bars judicial review of formally selected or ordered remedial
actions, i.e., a specific remedial option that EPA has selected
in a Record of Decision ("ROD") after notice and an opportunity
for public comments. See, e.q., Plaintiffs' Mem. in Response and
Opposition to the Mot. for Summary Judgment of the United States
("Plaintiffs' Opp."). This extraordinarily narrow view is flatly
contradicted by caselaw from the Seventh Circuit and other courts
and by the statutory text, and, if adopted, would open a massive
loophole in the well-established interpretation of section
113(h).
STATUTORY BACKGROUND
Section 104 of CERCAL authorizes EPA to undertake two broad
types of "response actions," i.e., "removal actions" and
"remedial actions." 42 U.S.C. # 9604(a)(1). Removal actions may
include both information-gathering efforts (e.g, investigation,
analysis, and monitoring) and efforts to reduce the release of
hazardous substances. See 42 U.S.C. # 9601(23) and 9604(a)(2);
40 C.F.R. # 300.415. Remedial actions are "those actions
consistent with permanent remedy taken instead of or in addition
to removal actions," and are generally more comprehensive
efforts. 42 U.S.C.#9601(24). Section 106 authorizes EPA to,
among other things, issue "such orders as may be necessary to
protect public health and welfare and the environment. n 42
U.S.C. #9606(a).
Section 113(h), 42 U.S.C. . 9613(h), provides that "no
Federal court shall have jurisdiction . . . to review any
challenges to removal or remedial action selected under section
9604 of this title, or to review any order issued under section
9606(a) of this title," except in certain situations, including
an action under section 9659 of this title (relating to
citizen suits) alleging that the removal or remedial
action taken under section 9604 of this title or
secured under section 9606 of this title was in
violation of any requirement of this chapter. Such an
action may not be.brought with regard to a removal
where a remedial action is to be undertaken at the
site.
42 U.S.C. # 9613(h)(4).
RESPONSE TO PLAINTIFFS STATEMENT OF MATERIAL FACTS
Plaintiffs assert that there are continuing releases of PCBs
at the three sites, and that "no such further remedial action has
yet been selected by EPA under CERCLA sections 104 and 106 but-is
merely being considered." Plaintiffs' Opp. at 2-3. In
Plaintiffs' view, a remedial action is only "selected under
section 104" when it is "formally chosen and committed to by EPA
under the procedures specified in CERCLA." Plaintiffs elaborate
that a remedial action must be "selected or secured under the
required CERCLA remedy selection procedures, including the public
participation procedures." Id. at 6. Even "definite proposals
for future action" do not qualify as remedial actions in
Plaintiffs view, until such proposals are "reflected in a ROD."
Id.
For example, the United States established in its opening
brief that EPA is addressing the threat posed by PCB
contamination at the Lemon Lane Landfill in three operable units,
or OUs, with each OU focusing on a different aspect of the
threat. United States' Mem. in Support of Mot. for Summary
Judgment ("U.S. Mem.") at 6-7. The first OU, control of the
source of the PCBs, is complete, but the second and third are
still in the initial, information-gathering stage, to determine
the best remedial options. Id. Plaintiffs do not dispute these
facts, they only assert that EPA has not yet "actually selected
or secured" the work to be done in these additional OUs.
Plaintiffs' Opp. at 4.
The United States agrees that EPA has not yet selected a
remedy for the water and sediments at the three sites, but
asserts that this fact is not material to the Court's
jurisdiction. Rather, as shown below, section 113(h) bars
judicial review even when EPA is in the initial data-gathering
stages of a cleanup, just as much as it applies to the
implementation of the cleanup once a remedy is selected.
ARGUMENT
A. Section 113(h) Bars Judicial Review of Incomplete
Removal and Remedial Actions, Before and After The
Remedy Is Selected.
As noted above, Plaintiffs, argument proceeds from a faulty
assumption. Section 113 (h)'s bar on judicial review does not
begin to apply only when EPA formally selects a remedy in a
Record of Decision. Rather, it also applies well before then,
when EPA is in the initial data-gathering stages of a cleanup.
See Schalk v. Reilly, 900 F.2d 109~, 1097 (7th Cir. 3990)
("challenges to the procedure employed in selecting a remedy
nevertheless impact the implementation of the remedy and result
in the same delays Congress sought to a-void by passage of
[section 133(h)").
Applying Schalk, the court in Cooper Industries. Inc. v.
EPA, 775 F. Supp. 1027 (W.D. Mich. 1991), rejected the precise
argument Plaintiffs advance here. In Cooper, a potentially
responsible party sought to prevent EPA from selecting a remedial
action and issuing a ROD without further public participation,
arguing that section 113(h) did not bar review because "no
response action has yet been selected." Id. at 1035, 1037. The
court held that the purpose of the bar on judicial review is to
"prevent litigation that may delay rapid cleanup . . . [a]
principle that is no less applicable where a party seeks
injunctive relief on the eve of EPA's remedy selection and Record
of Decision." Id. at 1039.
The plain text of the statute supports this conclusion. As
explained above, CERCLA defines "remedial action" broadly, to
include "those actions consistent with permanent remedy" of the
contamination. 42 U.S.C. . 9601(24). See also Cooper, 775 F.
Supp. at 1038 (statute and its legislative history shows Congress
intended section 113(h) to cover "all issues that could be
construed as a challenge to the response").
Plaintiffs do not contest that EPA is actively gathering
information to support additional cleanup decisions at each site.
See U.S. Mem. at 6-8. Nor do Plaintiffs contest the statements
by Tom Alcamo, EPA's Remedial Project Manager, that (a)
additional response action remains to be done at all three sites
to address water and sediments, and (b) the water and sediments
should be addressed before the Court evaluates the effectiveness
of the overall remedy, because the individual OUs were never
intended to judged in isolation. Id. at 9, 12. The information
gathering and decision making process currently underway here,
like the RI/FS process challenged in Cooner, is "consistent with
the permanent remedy" for these sites, 42 U.S.C. . 9601(24), and
therefore beyond judicial review until after the remedial action
is completed.
Plaintiffs' argument amounts to nothing more than an
assertion that the first stage of the remedial action is complete
at each site, and that EPA has not yet selected a remedy for the
additional stages. The Seventh Circuit has already rejected
Plaintiffs' argument that section 113(h) allows challenges to
completed stages when further remedial action "remains to be
done." Frev v. EPA, 270 F.3d 1129, 1134 (7th Cir. 2001).
Plaintiffs should not be allowed to relitigate that question
here. The only question for the Court in this litigation is
whether the removal or remedial actions at the Lemon Lane
Landfill, Neal's Landfill, and Bennett's Dump are complete within
the meaning of CERCLA section 113(h), 42 U.S.C. . 9613(h). EPA
has presented unrebutted evidence that these cleanups are not
complete; Plaintiffs only response is that the first stages are
complete, and EPA has not yet selected the remedy for the
additional stages.
Plaintiffs focus on the Seventh Circuit's instruction that
section 113(h) is "geared to concrete, existing, remedial
measures; not measures that might be devised at some future
time." Frev, 270 F.3d at 1134. From this language, Plaintiffs
deduce that "existing remedial measures" must mean removal or
remedial actions which have been included in a final record of
decision at the time a lawsuit is filed. -Plaintiffs' Opp. at 8.
However, the Seventh Circuit was not so restrictive. The
court explained that it was concerned that judicial review not be
delayed ``merely because there is a hypothetical possibility that
later monitoring might lead the EPA or the state authorities to
devise a follow-up remediation plan." Frey, 270 F.3d at 1134.
This is not such a case. As the United States' opening brief
establishes, the work completed to date was never intended to
stand on its own as a remedy. The RODs for Lemon Lane and Neal's
Landfill explicitly state that the hotspot excavation is only the
first stage of the overall remedy. See, e.q., Record of Decision
Amendment for the Source Control Operable Unit at the Lemon Lane
Landfill at 21 (attached as Ex. B to Plaintiffs' Opp.) ("All of
the alternatives, including complete removal of the landfill,
will require additional investigations and subsequent remedy
determinations for long-term water treatment and sediment removal
in Clear Creek.") (emphasis added); Record of Decision Amendment,
Source Control Operable Unit, Neal's Landfill, Monroe County,
Indiana at 3 (attached as Ex. C to Plaintiffs' Opp.) ("Subsequent
actions are planned to address fully the principal threats posed
by this site. Future remedial decisions will be made regarding
additional interim and final water treatment and sediment
removal.") (emphasis added).
Although no one can know what the precise remedy will look
like for water and sediments until the current information-
gathering and analysis effort is complete, the need for
additional remedial action at these sites is not hypothetical.
Nor is this a situation where a remedy is complete and its
success or failure is being monitored. See Frev, 270 F.3d at
1134. These are "active steps designed to cleanup a site,' that
EPA anticipated would be necessary from the beginning of the
remedial process. As such, they are within section 113 (h)'s
bar on judicial review until the entire remedy is completed.
B. Plaintiffs' First Amended Complaint does not raise any
new claims.
Plaintiffs, original Complaint, filed April 20, 2000,
included 12 counts. Plaintiffs' First Amended Complaint, filed
March 4, 2003, rearranges these counts, but does not add any new
claims to this litigation.
Due to che length of Plaintiffs' Complaint and First Amended
Complaint, the United States summarizes the counts in each in, the
table below, and the pages on which they begin:
| Count |
Complaint |
Page |
First Amended Complaint |
Page |
| 1 |
Arbitrary approval of hotspot remedy |
l9 |
Imminent and substantial endangerment |
ll |
| 2 |
Arbitrary selection of remedy without an RI/FS |
36 |
Arbitrary selection of remedy without an RI/FS |
38 |
| 3 |
Failure to follow RCRA, TSCA, and other requirements governing landfills
|
52 |
Failure to protect health and the environment |
52 |
| 4 |
Imminent and substantial endangerment
|
59 |
Violation of CERCLA's public participation requirements |
59 |
| 5 |
Nuisance |
90 |
Violation of CERCLA's remedy selection criteria |
62 |
|
6 |
Failure to protect health and the environment
|
91 |
Failure to enter settlement as a consent decree |
64 |
| 7 |
Violation of state air pollution laws |
94 |
Violation of 1985 Consent Decree |
65 |
| 8 |
Violation of CERCLA's public participation
|
95 |
Failure to perform an EIS |
66 |
| 9 |
Violation of CERCLA's remedy selection criteria |
96 |
Failure to follow RCRA's requirements governing landfills |
71 |
| 10 |
Violation of the Clean Water Act |
96 |
Failure to follow TSCA's requirements governing landfills |
75 |
| 11 |
97 |
Failure to enter settlement as a consent decree
|
Violation of the Clean Water Act |
75 |
| 12 |
Violation of 1985 Consent Decree
|
101 |
Arbitrary approval of hotspot remedy |
76 |
Plaintiffs have dropped their nuisance and state air
pollution counts (see Complaint Counts 5 and 7), divided their
RCRA and TSCA allegations into separate counts (compare Complaint
Count 3 with First Amended Complaint Counts 9 and 10) and added a
claim under the National Environmental Policy Act (see First
ended Complaint Count 8~. The NEPA claim, howeve w ais
and addressed in the briefing on Plaintiffs' TRO motion, and is
barred by section 113(h) to the same extent as Plaintiffs' other
claims. See, e.q., Schalk, 900 F.2d at 1091, 1097 (barring
review of NEPA claims brought pursuant to the APA) ; see acnerallv
United States, Opposition to Plaintiffs' Motion for Temporary
Restraining Order and Preliminary Injunction at 7 (filed May 15,
2000).
AS in the original Complaint, Plaintiffs seek both a
declaration that EPA and Viacom are in violation of various
statutes, and injunctive relief that will halt ongoing remedial
actions. See, e.c~, First Amended Complaint at 91 ("the Court
should . . . B) Order the Defendants to cease all activities
contributing to these violations . . ."). Plaintiffs' Prayer for
Relief even goes so far as to specify what remedy EPA should
implement:
E) Order that EPA shall issue a new ROD for the
Bloomington contaminated sites that provides for
complete removal of the contamination from the sites
and eventual treatment of the removed waste using non-
incineration technology (with above ground vaulting of
the removed waste until a proper treatment technology
and plan can be identified and implemented) . . .
Id. at 92.
This request for relief demonstrates that Plaintiffs'
claims, if allowed to proceed at this time, would gut the
statutory limit on judicial review and would contravene Congress'
fundamental purpose in enacting section 113(h), i.e., to prevent
litigation from delaying cleanups. See generally Schalk, 900
F.2d at 1097 ("judicial review itself slows the process down,"
resulting in the very delay Congress sought to avoid); Alabama v.
EPA, 871 F.2d 1548, 1559 (llth Cir. 1989) (a request to enjoin a
remedial action plan is a challenge to that plan).
Because Plaintiffs, claims in the First Amended Complaint,
like those in the original Complaint, seek judicial review and
oversight of remedies that are not complete, the Court should
dismiss this action as barred by CERCLA section 113(h).
CONCLUSION
For the foregoing reasons, the Court should grant the United
States' motion for summary judgment.
Respectfully submitted,
THOMAS SANSONETTI
Assistant, Attorney General
Environement & Nat. Res. Div.
1. In addition, Plaintiffs statements about what is or is not a
remedial action, and about how a remedial action is "selected,"
are legal conclusions and therefore not properly the subject of
material facts.
2. At Bennett's Dump, unlike at Lemon Lane and Neal's Landfill,
EPA has not issued a ROD Amendment, but the uncontroverted
affidavit of Tom Alcamo establishes that, as at the other sites,
"EPA intends to take additional steps to address these continuing
releases," but "needs the information Viacom is collecting in
order to determine the best approach . . ." Affidavit of Tom
Alcamo at #10 (attached as Ex. l to U.S. Mem.).
|