|
|
Karst Conduit Summary
Viacom Presentation
March, 2003
Major Questions in the Karst Study
- What is the source of PCBs that impact
the ICS during non-storm periods
- Where is the source of PCBs that impacts
the ICS during storms
- What causes the PCBs to move from the
source to the conduit system
- What are the specific pathways taken
- How can we prevent the movement, or
deplete the source of
What is the PCB Source?
- The source is multiple DNAPL sumps
- Indicated by high level of PCBs during storms
which significantly exceeds the solubility of PCBs in water
- PCBs do not correlate well with TSS
indicating some free phase material
- Dnapl pools have been found in the epikarst
at the site
- Dnapls have been found in the epikarst
- High levels of PCBs have not been found
anywhere else
- An epikarst source is consistent with the low flow
and storm flow data
- Much more PCB was found in the SE corner
during the remedy
- A phreatic sump could also explain the transport
data but is not indicated by the phreatic well
PCB results and pump tests
Conclusions on Revised Fence Diagram
- Some lithologies are more amenable to
solutional development brecciated
dolostones, dense brittle micritic limestone
- Brecciatecl dolostones may have been gypsum
cemented easily dissolved
- Some conduit zones may have been water table
related in their development
- Implies that larger, relict conduits may exist at
that level, and not just anastomosing channels.
Conclusions for the October-November
2001 Natutral Gradient Dye Test:
-
Some of the Fluorescein flushed from EF6 traveled to
Valhalla Cemetery in vadose passages.
- Some of the Fluorescein did descend to the phreatic
zone near well 00370.
T
- he Fluorescein response at IC Spring indicates there
may be more than pathway from EF6 to the spring.
- No dye was detected at SIaughternouse Spring. This
spring was samplecl sporaclical~y for up to ~ week after
injection. This indicates that this spring does not receive
site related waters quickly and is consistent with
previous dye testing that showed this site to most likely
be a minor discharge area for site waters. ~
- There was no breakthrough curve for Fluorescein at
Quarry B Spring or the weir seep. This indicates that
these springs are not carrying ~C Spring unclerflow
waters.
- Eosine appeared to trave'to the east-northeast.
- Eosine was not detectecl at any spring. This implies
either that the Fluorescein path to IC Spring is quicker
than the cosine path or that the cosine was diluted below
detection at the springs.
- Phloxine was not detected. This implies either that the
Fluorescein path to IC Spring is quicker than the
Phloxine path or that the Ph~oxine was diluted below
detection at the springs.
MW-21 Dye Results During Pumping
- This well did receive an cosine breakthrough curve
during the dye test without pumping. This indicates it is
near a path that carried cosine from the NN700 area (the
southwest corner of the site).
- This well did not have Fluorescein or Phloxine detections
during the October 31 dye test but did receive these two
dyes within 30 minutes of the start of pumping the well
on November 7. This indicates that at least some
portion of these dyes flowed near the well.
- The well received a detection of Fluorescein after
flushing EF6 on November 8. This indicates that at least
some of the Fluorescein flushed from EF6 does get
captured by this well when pumping.
- However, the IC Spring also received a large detection
of Fluorescein from the November ~ flush indicating that
pumping this well cannot capture all of what is flushed
from the EF6 area. Relatively speaking, the amount of
Fluorescein recovered at the spring after the flush was
much larger than that recovered at this well.
- This indicates there are two flow paths for waters
flushed from the EF6 area and that this well is near the
smaller of the two. This further indicates that this well is
not an efficient pumping location to capture materials
flushecl from the epikarst at EF6. This is supported by the
low level of PCBs recovered in the well since the
epikarst at EF6 has been shown to contain high levels of
PCBs.
- At the very beginning of pumping there were no
significant levels of any of the recently injected
dyes.
- After 8 hours of pumping Fluorescein begins to
show up at low levels. These levels build a
breakthrough curve with a peak 28 hours after
pumping began. The magnitude of the
Fluorescein levels are low relative to those
recovered at MW21 or IC Spring.
- Sporadic hits of cosine are also periodically seen after ~
hours of pumping. Curiously, there is not a breakthrough
curve for cosine after the NN700 well is flushed on
November ~ 5 at ~ ~ :30. However, the cosine is more
consistently present for the next 20 hours after the flush.
- No Phloxine is detected in the well even after SP1 was
flushed on November 14.
- A second low level breakthrough curve for Fluorescein is
seen starting 8 hours after LF6 is flushed on November
16. This indicates that at least some of the Fluorescein
flushed is captured by this well.
-
Phloxine does not take a path from SP] to
the IC Spring which is influenced by this
well.
- The eosine pathway is somewhat
influenced by this well but not to a
significant extent.
-
Minor portions of the F~uorescein pathway
can be influenced by this well.
Distance-Drawdown Relationships
- In MW-21 pump test drawdown in wells
follows distance from the pumped well.
- MW-17, the closest well, has the most
derawdown.
- MW-8s, the farthest well, has the least
drawdown.
- In MW-16 pump test, MW-17 drawdown is
displaced.
- MW-6, NN-625, and MS-1 all have more
drawdown than MW-17, even though it is
closer to the pumped well.
- Max. drawdown v. distance (Nov.16) show
displacement of Area-4 wells.
- MW-21 is affected by a recharge boundary
is is nearer a main conduit.
- Area-4 wells are nearer the recharge
boundary/major conduit.
- MW-17 is north of the recharge boundary
in relation to MW-16.
April 2002 1000 gallon flush of LF-6-8"
- 1032 gallons of water was flushed into
Piezomeler EF-6-8" along with 50 grams of
Fluorescein
- dye breakthrough curves were seen in wells OO-370 and 00-300A in-
- The first appearance of the dye at IC Spring occurred 11 hours after injection. A clear breakthrough curve peaking at 387 ppb at 13 hours after flushing is shown. However, the PCBs are hardly elevated at all.
Storm Tracer Test from LF6-4" Piezometer
On May 6, 2002 300 grams of Fluorescein dye was
injected with 10 gallons of flushing water in piezometer
EF6-4" at 13:10 hours. This took place at the beginning
of a 0.43" storm event, followed by a 0.97" and a 1.14".
The first rain induced a PCB peak of 20 ppb but no dye
peak.
The 2nd and 3rd rains induced sizable PCB peaks
Dye peaks are delayed 6 and 5 hours respectively from
the PCB peaks in storms 2 and 3 .
It seems apparent that the high PCB storm pulse does
not originate at EF6-4".
There seem to be three categories of traces with
regard to travel time from the site to IC spring.
They would be:
- Those tracer injections which are never
detected.
- Tracer travel limes significantly longer
than predicted.
- Tracer travel limes comparable to that
preclicted by the empirically derived
equation based on high PCB storm pulses.
Within the first category would be:
- The October 2001 injection of Phloxine B
into SP-1.
- The October 2001 injection of Eosine into
NN-700.
- The July 2002 injection of Fluorescein into
MW-6.
- The October 2002 injection of F~uore-scein
into MW-6.
- The October 2002 injection of Rhodamine
WT into OO-370.
The second category would contain:
The May 1996 injection of RWT into North
Sink.
The October 2001 injection of FLR into EF-6-
8".
- The May 2002 injection of FLR into LF-6-4 .
- The August 2002 injection of RWT into NN-
300A.
- The October 2002 injection of FLR into MW-16.
The third category would contain:
- The May 1996 injection of FLR into MW-7 area
macropores.
- The April 2002 injection of FLR into LF-6-8".
- The July 2002 injection of RWT into MW-4i.
- The August 9002 injection of RWT into PZ-F.
- The October 2002 injections of RWT into MW-18
Conclusions
- Traces that never produce break through curves at the
spring represent areas that are not drained by major
phreatic tributaries.
- Tracer travel times that are significantly longer than
predicted by the PCB storm pulse regression represent
locations that are "farther" from the spring, for example -
North Sink, in terms of length of phreatic conduit.
Another aspect of "distance" may also be lateral travel in
the vadose zone.
- Locations where the tracer travel times match the PCB
storm pulse are candidate locations for investigation as
possible source areas for the PCB storm pulse.
- Despite the puzzle of 00370, the pattern
emerges of phreatic convergence to the east
side of Lemon Lane.
- Tracer locations in Valhalla have either
produced no break through curves or delayed
passage to the spring.
- This implies that the high PCB pulse does not
originate in the Valhalla area, but lies north of
the tracks under the Lemon Lane site itself.
Epikarst Well Level Data
Non-Storm
- Pump Tests indicated that LF1 and LF5 have
some partial connection and that LF2 is not
connected to either
- EF5 usually has the higher level during non-
storm conditions. This indicates flow to the
south
- Based on pump test data, LF5 appears relatecl
to a bigger reservoir than LF1
- Assumed leakage rates from either during non-
storm conclitions appear small (< 1 gallon per
hour)
Phreatic Well Level
Storm Data
- Well level vs flow at IC Spring
- Some wells have more divergence from linearity in
the rising limb (MW6, MW19, MW4S). This may
indicate local recharge.
- Wells sometimes show large slope changes on the
receding limb vs IC Flow.
- Well levels from data loggers (at higher base
flows) also show the MW4 area as the low
- On the east side, MW4S and MW19 rise faster
during early rising limb of storms as does MW6
in Valhalla
Epikarst Well Level
Storm Data
- LF 1, 2 and 5 respond to even small
storms
- LF5 has shown the highest recorded water
level around the site at almost 870 feet
amsl during a storm. Suspect this would
have been significantly eclipsed during the
Oct 2000 event
- Relative levels show flow from LF5
towards LF1 during storms
- LF6 and 7 respond
- EF6/7 response does not appear related to the
LF1, 2, 5 responses although it is possible the
secondary responses could be related
- LF7 appeared to receive storm water from a
quick run-off source possibly the cap
- The only source of cap run-off near LF7 is the
south slope area, this implies flow to the
north/northeast
- Relative levels between LF6 and 7 do not show
a consistent flow direction
Well Temperature Responses
- A great deal of temperature measurements exist
for wells around Lemon Lane
- Interpretation of the data is complicatecl by
- a lack of literature on the subject
- data quality and comparability issues
- Location of sensor in the well
- Bad instrument data
- Large scale weather changes
- Our strategy was to start with known events and
derive a theory for temperature changes
consistent with known drivers
Known Facts about Well Temperatures
- Epikarst water under the landfill was much warmer than
phreatic water.
- Storm water has a significantly different temperature
than aquifer water during certain times of the year.
- Non-storm temperatures in wells do not follow surface air
temperatures. They tend to have annual thermal cycles
that are out of phase with surface air temperatures.
- The re-routing of site drainage to Sargent's Pond had a
major impact on MW7
- Wells do not show large temperature stratification
vertically
Well Temperature Responses During Pump Tests
- Long term pump tests
- MW21: note MW17 response and general lack of responese elsewhere
- MW16: larger response seen in MS1
- Short Term pump tests
Well Flush Test 12/11/02
Valhalla Wells
- 00370 did not show a temperature response when
flushing MW6, yet 00387did. Did we miss it because of
sampling interval in 370?
- 00387 showed a larger temperature response to the
MW6 flushing than to 00370 flushing
- Velocities
- MW6 to 00387 = 2.3 Ft/Min
- 00370 to 00387= 5.6 Ft/Min
- This implies that there is a conduit between 00387 and
00370
- Tentative response at 41 with a velocity of 1.8 Ft/Min
- No noticeable response in MW18
Well Flush Test 12/12/02
East Side Wells
- No flush water arrived at MW17
- Water flushed into MW18 arrived at 4I
within 25 minutes. Travel velocity of 3.4
Ft/Min
- Water flushed into MW4 area arrived at
MW18 within 40 minutes
- MW19 did not receive a major hit of any of
the flush water
Theories on Well Temperatures
- Well temperature is a result of a dynamic equilibrium and
changes in mass flux of water through a well will induce
a temperature change. This implies a continuous flow
vertically in the well bore during a transient.
- A level change by itself will not induce a significant
temperature change in a well
- A warm anomaly indicates an increase in epikarst flow
- Differences in well temperature response can be useful
in determining differences in local flow responses and
water sources
- A large storm temperature response is indicative of a
large flow change during the storm which indicates the
well is near an active storm induced pathway
Well Temperature Data Review
Non-Storm
Temperature profiles around the landfill
- Significant warm anomaly at MW19/18
- Warm anomaly at MW6
- Cold spot at 4 series wells
Well Temperature Data Review
Storm Data
- Most wells that are in the main phreatic
zone do respond during storms
- Deep wells do not respond
- Limited data on epikarst wells do not show
major responses
- Some main phreatic wells respond more than
others
- Direction of the response varies both with
season and location
- Some wells are obviously impacted by storm
water
- MW4I and MW21 have shown some
disproportionately large responses to
larger storms and in some cases smaller
events (MW4I)
- Oct 2000 event MW4I
- May 2002 event MW21
- Late 1999 MW4I responses
- Wells 8s, SP1 and MW7 (prior to lining this area)
respond at times like storm water run-off
- Wells MW6 and MW19 have larger responses at
limes
- MW6 did have relatively more water develop at the
815 horizon during drilling
- Direction of storm responses varies by season
and is not always consistent from year to year.
- See MW4I during 1999 and 2000
Epikarst Well Temperature
Responses During Storms
- LF7 appeared to receive storm run-off
water quickly
- LF1/5/2 do not show much of a response
- When LF1 did respond, it did not indicate
storm water
- LF6 predisturbance appeared to show a
muted storm water response
Well Temperature Review
Conclusions
- There are temperature anomalies around the landfill and in Valhalla
at non-storm conditions
- Most wells do show a temperature response during storms. Most
times these responses are opposite of what you would expect from
storm water. The direction of the response seems to vary
seasonally. No well we have to date appears to act like a well that
sees a large passage of storm water during a storm consistently.
- Any flow changes in the well will induce a temperature change.
These flow changes may be more vertical than horizontal
- Abnormally large temperature changes at a well during a storm relate
to large flow changes through the well. It is unclear if this indicates
a conduit or a local condition.
- MW4I and MW21 have shown some abnormal responses during
large events. It is not clear how to interpret these responses.
Summary of Basin/Aquifer
- Where are the major recharge areas
- Martin's Sink
- East side neighborhood
- West side of landfill
- North sink area
- Far east neighborhoods
- What zones are used for tow flow transport of
water and PCBs
- 798-800 zone: no storage available
- 815-818 zone
- epikarst zones supply water during low flow
- What zones are used for high flow transport
epiphreatic zones
- 820-823 zone
- When does Epikarst water move during a
storm
- Early flow responses indicated from well
levels and PCB response at spring
- When does site water get to ICs during a
storm
- Water arrival is indicated by PCBs which is
repeatable and determined by flows which
indicative of phreatic transport
PCB Data Review
- Concentration vs Flow
- Concentration vs Concluctivity
- Mass Rate vs Flow
- Comprehensive review of concluit testing
impact on low flow PCB levels at the ICS
- PCBs in Wells
- Recent Storm Samples
PCBs at ICS Non-Storm
- PCBs Concentration vs Flow
- PCBs Concentration vs Conductivity:
- Note: Conductivity clata may be impacted by road
salt in winter months
- PCB Mass Rate vs Flow:
- Note mass rate, indicates that mass per minute is
lower during dry periocis
- Assuming a 1000 ppb source strength, flow of the
source could be .25 to 2.5 gpm at non-storm
conditions
PCBs at ICS During the Flush Tests
PCBs at ICS During the Long Term
Pump Tests
- PCBs at ICS were impacted by MW21
pump test
- Mass rates increased after adjusting for
autosampler time
- PCBs at ICS were not significantly
impacted by the MW] 6 pump test
- Mass rates not significantly changed after
adjusting for autosamp~er times
PCBs at ICS During the Short
Term Pump Tests
- Data quality impacted by time in
autosamplers
- Tests were too short
PCBs at MW4 Area Wells During
Storm Sampling
- No well showed a significant increase in
- PCBs during the storm
- Most wells indicated dilution of PCBs
when concluctivity ciroppecl
- MW18 has the highest pre-storm PCBs
- MW19 showed the largest concluctivity
change during the storm
Proposed Epikarst Investigations
- Add new wells to the epikarst based on existing
geophysics in the SE corner
- Perform more dye testing during storm/non-storm
conditions to establish which epikarst wells mimic PCB
travel times
- Sample new wells for PCBs
- For those locations that match PCB travel limes, perform
pump tests to determine reservoir size and PCB removal
potential
- Utilize liming match locations as injection locations for
phreatic location testing
- Dye test storm run-off to identify source of flushing water and test for dyes in candidate epikarst wells
Proposed Phreatic Investigations
- Utilize found epikarst wells that match
PCB timing as injection locations
- Inject brine to enhance geophysical
signals
- Utilize time lapse electrical resistivity with
brine injections to illuminate pathway that
PCBs may take
- Drill pathway and perform sampling and
pump tests
Feasibility Testing
- Long term pump test from new phreatic wells
- Short term/long term pumping from epikarst
locations
- Storm run-off collection to eliminate flushing
source
- If source is identified and cannot be efficiently
removed, possible to try in-situ degradation
- Epikarst clean water collection/removal
|