Demoliton Schedule, Bloomington ABB Plant
August 28-September 10, 2006

Week of August 28th

Building Demolition

  • Set up water lines for asbestos abatement work.
  • Set up water lines for asbestos abatement work. Begin remaining ACM abatement (office area floor tile and plant area pipe wrap).
  • Set up water lines for asbestos abatement work. Clean and sample cranes and crane rails.
  • Set up water lines for asbestos abatement work. Complete office trailer set up and electrical connections.
  • Set up water lines for asbestos abatement work. Begin removal of freon from cooling units.
  • Set up water lines for asbestos abatement work. Set and calibrate truck scales for disposal of PCB contaminated asbestos.
  • Set up water lines for asbestos abatement work. Arrange for disposal of PCB contaminated asbestos.

Week of September 4th

Building Demolition

  • All personnel will be off Monday September 4 for Labor Day Holiday.
  • All personnel will be off Monday September 4 for Labor Day Holiday. Cut and cap site utilities
  • All personnel will be off Monday September 4 for Labor Day Holiday. Finish removal and load-out of any remaining universal Waste (freon for example).
  • All personnel will be off Monday September 4 for Labor Day Holiday. Set up storm water treatment system.
  • All personnel will be off Monday September 4 for Labor Day Holiday. Remove gravel from roof (vacuum truck) in preparation for removal of PCB contaminated building materials starting week of September 11.
Warning! Eat no fish from Clear Creek, Pleasant Run, Salt or Richland Creeks.

Home
COPA

For more info, e-mail info@copa.org.
Copyright © 1990-2002 COPA, Inc. All rights reserved.
See legal page for terms of use and disclaimers.
All trademarks belong to their respective owners.